Net Metering
Any consumer owned qualifying facility with a generation capacity of up to 10kW can tie into our electric distribution system.
Meters that are used with this program register positive (forward) for power used by you when needed from our electric system. The meter also registers negative (backward) for excess power generated by your system that goes back into our electric system. JMEC has already interconnected a number of PV systems all across our service area.
The process is simple:
Turn in Jemez Electric interconnect application, $50.00 application fee, site map and one line diagram.
Connect is then done after application approval, interconnect agreement is signed and electrical permits are cleared.
Download Interconnect Application ![]()
Download Consumer Guidelines ![]()
Download Certificate Completion ![]()
*If you are looking at something more aggressive, over 10kW, a more extensive application process and different fees will apply.
Contacts:
Engineering Department
(505-753-2105 or 1-888-755-2105
Email: vcoriz@jemezcoop.org
Related Links:
New Mexico Public Regulation Commission
New Mexico Commission on Public Records
Title 17 Chapter 9 Rule 568 - Interconnection up to 10kW
Title 17 Chapter 9 Rule 570 - Utility's purchasing requirements
New Mexico Solar Energy Association
Toll Free Line: 1-888-88-NMSOL Office Phone: 505-246-0400
http://www.nmsea.org
Renewable Energy Industries Association of New Mexico
Phone (505) 379-4662
http://reia-nm.org